|
The Texas Medical Center’s Tallest Building
Memorial Hermann Medical Plaza
Edward J. Ulrich, Jr.

Abstract
This paper focuses on the contribution of drilled piers in
making an awesome project spectacular. Drilled piers and shallow foundations
eliminated temporary retention systems to support the Texas Medical Center’s
tallest building at thirty-two stories. Reduced development costs amounted to
over $1 million when consideration is given to increased useable basement space,
eliminating cantilevered floors for one full bay to the property line, and
eliminating interior perimeter columns to effectively minimize the depth of
basement excavation. The unique foundation features of the building and parking
garage are highlighted along with the structural concepts for basement wall
design.
Drilled piers formed the temporary and permanent basement
wall along with the sole support for thirty-two stories of exterior column loads
of the reinforced concrete tower. The drilled pier design considered
installation only by Slurry Displacement Method in general accordance with ACI
336.1-89 and 01 specifications and modified for site-specific design. Pier
design details are furnished along with the a concrete mix design and and
inspection results of the completed piers to the base of the basement
excavation. The Design Geotechnical Engineer investigated, designed, constructed
engineered, and monitored.
Introduction
The Memorial Hermann Medical Plaza and Garage emerged as The Texas Medical
Center’s Tallest Building and the beacon to visitors pilgrimiging from the
Houston Central Business District. Unlike the super towers which exploded the
Houston Skyline by the early 1980’s: the 75-story Chase Tower, the tallest soil
supported building, 64 – story Williams Tower, the tallest suburban office
building, and the 72 story Wells Fargo Tower, the Memorial Hermann Medical Plaza
was under very strict budget controls and maximum site utilization was a must to
provide the needed long-term margin for medical care. The development is shown
as a west elevation in Figure1.

The 32 story building has many unique characteristics that make the structure
a monumental technical achievement to continue challenging the 21 st Century.
The combination of several unique foundation features especially multiple
foundation systems reduced development costs by over $1 million and added to the
building income by $1 million. In summary these foundation features are:
The development is the southwest’s tallest soil supported building on
multiple foundation types
The excavation-bracing system was designed to form the temporary and
permanent basement wall and the wall was the deepest cantilevered system
in the Houston Area
Basement walls supported the exterior columns of the 32 story tower
on three sides; spread footings were used to support exterior column
loads on one side
Mat supported the building core
Drilled pier soldier piles were installed with bentonite slurry
following the ACI Specification for the Construction of Drilled piers (ACI
336.1-89 and 01), the only known use of the ACI specifications locally.
The Construction Geotechnical Engineer provided the site services for
evaluating the insitu conditions and the compliance with the
construction means and methods needed for design.
Drilled piers with shallow foundations combined to make an awesome project
spectacular.
Project Description
Architectural and Structural Features.
The building expresses the crispness, cleanliness, quality, and
progressiveness of the Texas Medical Center. The design captures the spirit and
architectural character of Houston with the strong optimistic image of the
Memorial Hermann Team, fig1. The office tower is 240 ft by 274 ft (73m by 84m)
in plan and is situated at the entrance to the Texas Medical Center, the north
end of the site, Figures 1 and 2.

The building has 500,000 gsf (46,500 sq m)of medical office space with garage
parking for 2500 vehicles that covers an area ao over two city business district
blocks for a total structure area of 1.5 million sq ft (140,000 sq m). The
parking garage is the largest modern garage of its kind built in Houston. The
reinforced concrete tower rises 32 floors above a two level basement that had an
excavation depth of 29 ft (9m) to the base of foundations with a plan geometry
of 237 ft by 200 ft (72 by 65 m). Six levels of parking and one basement level
extend 250 ft (76 m) south of the tower south face. The garage basement extends
into the tower so that two basement levels are beneath the tower and part of the
garage, Figure 1.
Finished floor levels of Basement level 2 and Basement Level 1 are 22 ft (7m)
and 12 ft (4m), respectively.
An excavation retention system was needed because the project extended to the
property lines in the Texas medical Center and the most heavily traveled streets
bordered the property on three sides with an extensive network of utilities. To
minimize the use of property for temporary excavation retention, designing the
underground structure to function for both temporary and permanent condtions was
the cost effective approach selected. Drilled piers, 42 in.(110 cm) dia. At 18
in. (46 cm) clear spacing , were selected for the temporary basement wall to
satisfy both of the requirements of the construction cantilever wall design and
support of the perimeter columns. Accordingly the all exterior columns for the
tower and garage were supported on the basement wall to avoid cantilevering the
structure floors and reducing the interference of perimeter columns on the
north, east, and west sided of the tower, fig 2. The south side perimeter
columns at the garage transition are supported by large spread footings. A mat
foundation is used to support the Tower core. Intermediate columns along to
ease-west axis are supported by drilled pier groups.
Foundation Characteristics
The development foundations are divided into five
systems:
Drilled piers 42 in. dia. Designed as a cantilever arranged in a
single line group along three sides to form the temporary excavation
wall, permanent basement wall, and full foundation support for the
building and garage exterior columns
Shallow spread foundations to support the interior garage loads
Mat foundation to support the interior building core
Mini mats 30 ft by 15 ft in plan that support the exterior building
columns bordering the parking garage
Six-pier groups to support intermediate columns between the mat and
basement wall along the east-west building axis
Although the building floor slab in Basement Level 2 is 20 ft below street
level, the building mat foundation base extended 29 ft below street level and
the garage foundation bases were 16 to 18 ft below street level.
The drilled pier retaining wall along with using multiple foundation systems
exploded the project success because the piers allowed maximum efficient
utilization of the property. Although we considered auger cast in place piles,
we chose drilled piers installed by the Slurry Displacement Method because the
fewer variables to control in construction made the use of piers a more
steadfast foundation system and the reinforcing could be installed in advance of
concreting instead of attempting reinforcing installing after grouting.
The edge of the core mat was limited so that the pier cantilever could be
designed only for the lateral earth pressure between the street level and top of
Basement Level 2 floor slab and the axial loads from the structures. Pier
sections were 42 in. dia. by 86 ft bordering Basement Level 2 and 30 in dia by
40 ft along the Parking Garage Basement level 1.
Drilled Piers. A total of 379 piers were installed by the Slurry
Displacement Method consistent with ACI 336.1-89 and 01 based on a design
principally made by the Design Geotechnical Engineer and Project Specifications
prepared by the Design Geotechnical Engineer. Nearly 180 piers were 42 in.
diameter by 70 to 120 ft to support the exterior columns of the thirty story
building, act as the temporary excavation wall, and permanent basement wall. A
total of 202 piers at 30 in. diameter were installed to depths ranging from 37
to 92 ft to achive the same objectives as the large diameter piers , but for a
one story basement.
Pier clear spacing was typically 18 in. Reinforcing amounted to 1.2 to 1.3%
of the pier cross sectional area using an asymmetrical spacing for efficient use
of pier reinforcing steel. Although the reinforcing spacing was initially
designed for a minimum clear spacing of 4 in. or 4 times the size of the maximum
coarse aggregate, the Geotechnical Engineer acquiesced to a smaller clear
spacing of 3 in. consistent with past positive experiences with strong
construction engineering on site.
Pier Concrete. The pier concrete mix, Table1, was used successfully on
past projects with the supplier and was again confirmed for suitability by trial
batch for maintaining a 6 in. slump for 4 hrs because cement manufacturers and
mid-range retarder product manufacturers had changed since the last use of the
mix with these design properties.
|
Table 1
Drilled Pier Mix Design
Slurry Displacement Method
Per Cubic Yard |
|
|
Mix Ingredient |
Quantity
lbs |
|
Cement, Type I |
|
|
Fly Ash, Type C |
|
|
Sand, ASTM C33 |
|
|
Coarse Aggregate: ¾" to ¼"
Rounded grains |
|
|
Water |
|
|
|
|
|
|
|
|
|
General Subsurface Conditions
The general subsurface conditions are variable between soil borings,
consistent for Houston Area deep excavations, Table 2. Beyond the surface fill,
the underlying soils are medium to strong clay with sand and silt inclusions at
varying thicknesses and positions. From the base of the fill to about 30 ft
below street level, the soil is clay with a distinct but discontinuous silt zone
from 70 to 80 ft below street level. The clay grades to dense silty fine sand
below 30 ft to about 60 ft. Strong clay are below the sand.
The Undrained shear strength of the clay soils below about 10 ft is more than
0.7 tsf and becomes more than 1.0 tsf below the upper sand. The sand and silt is
medium dense to dense in condition provide the groundwater is controlled
properly during site excavation. The sand and deep clay have siltstone
inclusions at varying positions but generally smaller than 2 ft. The depth to
ground water was measured to be 24 ft below the ground surface in the upper sand
and slightly deeper in the zone from 70 to 80 ft depth.

|
|
|
Table 2
General Subsurface Conditions |
|
|
Depth
Below Street
ft |
Soil Description |
Undrained Shear
Strength Estimate
tsf |
Standard Penetration
Resistance
N-Value |
|
0 to 8 |
FILL: Firm to Stiff
Clay with Demolition
Debris |
0.24 to 0.6 |
|
|
8 to 32 |
Stiff to very Stiff Clay,
slickensided |
0.65 to 1.25 |
|
|
32 to 65 |
Dense Silty Fine Sand
With siltstone inclusions |
|
22 to 50 |
|
65 to 70 |
Very stiff Clay |
1.20 to 1.56 |
|
|
70 to 80 |
Dense Silt |
|
26 to 35 |
|
80 to 150 |
Very stiff to hard Clay
With sand and silt inclusions |
1.50 to 2.6 |
|
Foundation Features
The shallow foundations in the structure interior consisted of a core mat for
the tower, mini mats 15 by 30 and spread footings 12 ft by 12 ft. The tower mat
was design using the DAM procedure initially reported by Ulrich (1995) for the
design of mat foundations and adjusted for local experience with tall buildings.
The assessment of building foundation movement was analyzed by extending the DAM
procedure to the perimeter walls considering Busssinesq and Wetergarrd Models.
The expected differential movement between the basement wall and tower core of
less than 1 in. was achieved by top out in June 2006.
Groundwater Level Control
Proper control of the groundwater is needed for both construction and long
term conditions. Inadequate groundwater control would cause the excavation to be
unstable and the mat subgrade would become quick resulting in catastrophic
building performance. A system of deep, 8 fully penetrating wells with
submersible pumps was installed outside of the tower to depressure and dewater
the building excavation. The temporary dewatering was not designed to allow
drilled pier installation by the dry methods because local experience has shown
that the dewatering system is seldom effective in preventing premature collapse
of the shafts below the original groundwater level. Combined flow to the
discharge location was 70 to 80 gpm.
The temporary system was replaced by an underslab, gravity system using a
double stage sand and gravel filter to PVC collector pipes designed and detailed
by the Geotechnical Engineer.
Drilled Pier Construction
Drilled pier construction followed the project specification prepared by the
Design Geotechnical Engineer in general accordance with ACI 336.1- (01) and
first used in Texas to define the pier construction method on major Texas
projects (Ulrich, 1990, 1995). Before the emergence of the new ACI pier
construction standard, piers installed by the slurry displacement method were
popular primarily with the Texas Department of Transportation and in Florida.
The principal parameters measured on this assignment were mud weight, mud
viscosity, tremie tip position, and concrete flow characteristics. Concrete
delivered to the pumping location not containing at least a 7 in . slump was
rejected. Except for 6 piers wherein the concrete was not expunged beyond the
top of concrete, all piers were clean smooth and free of significant defects to
the depth exposed in the excavation.

Fig. 6


Fig. 7
Example of an occasional hole only extending to the rebar.
The drilled pier installation process and results were an awesome improvement
over the results which occurred without a responsible pier installation standard
and needed construction engineering, Fig. 8.

Conclusions
Drilled piers
are a highly productive and economical foundation system that can be used
independently or with other foundation types to safely support structural loads
and accommodate architectural innovation in both temporary and long term
conditions. All foundation systems have the potential for defects. Flawless
construction is not possible, a distinct advantage of drilled piers over
Augercast piles is that pier construction using the Slurry Displacement Method
has less construction variables to control; hence, the risk for significant
defects should be less. Success in underground construction occurs with a team
commitment and the underground specialist contributes appropriately as a design
team member. The Memorial Hermann Medical Plaza now stands as a welcoming
beacon to those in search of innovative medical care.
Acknowledgements
The author
gratefully acknowledges the Memorial Hermann Hospital System for their
innovation and focus in design and construction. The Mischer Development
Corporation developed the project and provided guidance where light was hard to
find under the leadership of Robin Harrison. Harvey Construction Company as the
contractor, led by Kelly Hall, was well organized and committed as the best of
the best. Kirksey Architects, led by Jim Deitzman, are appreciated for both
their architecture and sensitivity to construction. Some may say such attributes
are opposites. Not enough can be said about Haynes Whaley Associates, Structural
Engineers who always left the closet door open and the key in the hands of the
Design Geotechnical Engineer. Thankyou to Robert Tyler and Ronal Chen. From top
to bottom, a dedicated design-build team conquered the unthinkable and the
result was significant cost savings for ownership. Bell Bottom Foundation
Company was superb as usual and TXI was exemplary in providing the pier
concrete.
References
Ulrich, E. J. (1995). Subgrade Reaction in Mat Foundation Design, ACI
SP-152 Design and performance of Mat Foundations, A State of the Art Review,
Farmington Hills, MI, pp 95- 116.
Ulrich, E. J. and Ehlers, C.J. (1995). Tallest Building in the Texas Medical
Center: St. Luke’s medical Tower, ACI SP-152 Design and Performance of
Mat Foundations, A State of the Art Review, Farmington Hills, MI, pp 219- 244.
Ulrich, E.j. & Ehlers (1990). Arrest of a Texas Landslide, Concrete
International, ACI, Farmington Hills, MI.,pp
|